CONSTRUCTION OF THE REMAINING WORKS OF THE 'RECREATION OF LAKE KARLA' PROJECT – 1ST PHASE

This includes works such as:

  • The expansion of the embankments of collector S3 up to k.p. 16+000 approximately
  • The completion of collector S6, with a total length of 2.5km, and the entry project for the diversion of the Kerassiotis torrent
  • Road construction works with the conversion of the Kastri – Amygdali road and the wetland access road
  • The construction of an artificial wetland covering an area of approximately 1,100 stremmas (equal to 110 hectares) for processing and treating the leachates of the region and channelling the water to the dam of Lake Karla
  • Clearing channel 1T along a length of approximately 30km
  • Draining the closed basins left of collector S3 and completing the stream confluence projects up to k.p. 16+000 approximately
  • Damming of seepage channels in the sealing embankment area