CONSTRUCTION OF THE PROJECTS REQUIRED FOR THE SUPPLY OF LAKE KARLA FROM THE RIVER PINEIOS

This project concerned the construction of:

  • The water supply project, with a pumping station at the river Pineios to supply Lake Karla with the autumn and winter runoff of the river
  • The installation of transverse and lateral sluices for the unhindered channelling of water towards Lake Karla, and
  • An embankment approximately 2km in length downstream of Collector S4 for safety reasons


Clearing and earthworks took place along the length of water transport system at the existing 2D - 6Τ - 7Τ - 2Τ - S4 canals – channels